This project was executed by CAPEX Projects who managed the design process and coordinated the design meetings for the newly constructed freezer store of DC Meat Wholesalers. DC Meat required additional space within their existing freezer facility which had 850 pallet allocations of fixed racking within 675 m² floor space.

DC Meat has 16 retail stores within the Western Cape and a freezer store that operates at -25˚C. The distribution teams deliver on average 500 000 kg of fresh and frozen products per week. DC is known as a wholesaler that imports and exports a variety of meat products. As part of their upgrade and expansion planning, a larger facility had to be reconstructed to accommodate increased production levels.
PROJECT REQUIREMENTS
Each appointed supplier had key responsibilities by which Barpro Storage had the responsibility of installing the rails and mobile racking system.
The key deliverables of the project in its entirety were:
- Refrigeration
- Insulation, Pods, Freezer door,
- Fire installations
- Freezer floor & repairs to receiving floor & structural aspects
- Racking & Rails
- Warehouse management systems and Security

THE MOBILE RACKING SYSTEM – BARPRO STORAGE SA
Barpro’s approach was to provide a system with a 2 phased process
Phase 1: Installation of rails & support stools
Phase 2: 4 Mobile bases with wooden bumper protection
The 4 bases have individual control. The mobile bases were installed at operational temperatures to prevent disruption to DC Meats’ daily activities.

Individual Control System which is a straightforward system that allows each mobile rack to be moved independently of the other mobile racks in a zone. Each rack can be moved left or right with a single press of the push buttons mounted on the front of each mobile rack.
- Total current storage capacity of 1130 pallet locations on Barpro mobiles
THE RACKING – UNIVERSAL STORAGE SYSTEMS
Universal’s Racking Superstructure is mounted on top of the Barpro mobile bases. The structure consists of frame load and base beams.

CONCLUSION
During the construction period the programme had to be amended to accommodate all parties, but the changes did not affect Barpro and Universal from completing and successful install rails, mobiles and racking system in short order.
The completed works were signed off and approved by the project managers of CAPEX projects and Mr Roberto Leao of DC Meat. The freezer store is fully operational.
COMPLETE INSTALLATION:
- Phase 1: Lining & leveling of ground rails – 13 September 2021
- Phase 2: Installation of Bases & Electrics – 15 December 2021
- The Racking Superstructure was completed simultaneously with the bases & electrics